LiveASX is an independent website and is not affiliated with, endorsed by, or associated with ASX Limited.

Boab Metals Extends Sorby Hills Mine Life As Construction Advances

Closing price · 2026-10-27: $0.310 · +1.64%

Boab Metals’ Sorby Hills plan extends the projected mine life from 8.5 to 10.5 years, with contained silver up 15% and lead up 10%, while project capital costs are reported as broadly unchanged. The resource estimate is 7% larger than in 2021, and construction is progressing toward first concentrate production in the third quarter of 2027; the company had approximately A$30 million in cash at quarter-end.

Based on BML’s ASX announcements · Latest release 27/10/2026 09:50 AM Sydney time
Story updated: 27/10/2026 09:56 AM

Source announcements:

More news from 2026-10-27 · Company history