Grange Resources backs North Pit underground project as quarterly sales and cash rise

GRR: $0.110 +4.76% · MC: $122M

Grange Resources made a final investment decision on the North Pit Underground Project, with development scheduled to restart in early 2027 and first ore expected in 2028; the company says the project is intended to extend production and pellet supply continuity to 2035. Quarterly concentrate production and pellet sales increased from the June quarter, while unit cash operating costs fell and cash and liquid investments rose to approximately A$300 million. The average realised product price also edged higher quarter on quarter.

Source announcements: 2026-10-28 09:39 to 2026-10-28 09:39 Sydney time
Story updated 2026-10-28 10:09 Sydney time
SourcesGRR - Quarterly Report for 3 months ended 30 September 2026