Frontier Energy Starts Waroona Site Works as Forecast Revenue and Cash Flow Rise
FHE: $0.180 -2.70% · MC: $217M
Frontier Energy says early site works have begun at its Waroona renewable energy project, with major contracts in place on fixed-price terms and project finance commitments of up to approximately $280 million agreed, though financial close is still expected. Following an increase in allocated reserve capacity, the company lifted its average annual revenue forecast to approximately $76 million, EBITDA to approximately $66 million and free cash flow to approximately $38 million; it also completed a $110 million equity raising and ended the quarter with approximately $75 million in cash.