Hastings Reports Thailand Plant Acquisition Completion And Yangibana Study Results

HAS: $0.200 -4.76% · MC: $53M

Hastings’ quarterly report highlights completion after quarter-end of its 49% acquisition of the Thailand processing plant, with first production targeted for the second quarter of 2027; the company is also pursuing approval and negotiations to raise its stake to at least 51%. The updated Yangibana study estimates a pre-tax project value of about $649 million against initial capital of about $333 million, with a 19-year mine life and a payback period of about two years. The Thailand plant’s planned capacity was increased from about 6,000 tonnes a year to about 12,000 tonnes, with upgrade work continuing.

Source announcements: 2026-10-30 17:46 to 2026-10-30 17:46 Sydney time
Story updated 2026-10-30 17:52 Sydney time