OzAurum Advances Mulgabbie North Heap-Leach Plans Despite Rain Delays

OZM: $0.065 -2.99% · MC: $20M

OzAurum reports completing two production water bores for Stage 1 and securing five key approvals, while heavy rain delayed site civil works and the heap-leach plant’s transport to site. Final column tests returned up to 95% gold recovery, following earlier column results of up to 82%; the company says these results will inform scoping and mine planning. The announcement also repeats the 95% result disclosed earlier this week.

Source announcements: 2026-10-30 09:22 to 2026-10-30 09:22 Sydney time
Story updated 2026-10-30 11:26 Sydney time