Pacific Lime and Cement Moves Into Equipment Installation as Lime Project Cost Forecast Nears Funding Limit
PLA: $0.380 +2.70% · MC: $364M
Pacific Lime and Cement says its Central Lime Project has shifted from civil construction toward equipment installation, with the first major shipment—more than half of the kiln and process-plant equipment and materials—arriving after quarter-end. The latest forecast cost is approximately A$129 million, within the A$133 million funding framework but toward its upper end; first lime production is targeted for late in the first quarter to the second quarter of 2027, later than the previously reported early-November start for equipment erection. The PNG Government’s investment for a 13% project interest has been received, while the Central Cement Project’s preferred EPC tenderer is targeted for selection by December 2026.