Tlou Energy Reports Coal Fines Disrupt Lesedi Testing As Kala Expansion Plans Advance
TOU: $0.001 -66.67% · MC: $3M
Tlou Energy continued testing and monitoring at Lesedi, but recurring coal-fines influxes and pump inefficiencies led it to temporarily shut down Lesedi 6; Kala Data Centre remained at proof-of-concept scale as the company assessed expansion requirements. The Lesedi substation is approximately 90% complete, with remaining work deferred pending funding, while the company reported approximately $57,000 in cash and about $2.9 million in available funding at quarter end.