Latrobe Magnesium Commissioning Reaches Halfway Mark As First Metal Target Holds
LMG: $0.013 -7.14% · MC: $56M
Latrobe Magnesium says its Phase 1B plant is 98% installed and commissioning has reached 50%, up from 25% at the end of September, with first magnesium metal still targeted by the end of 2026 and spending forecast within budget. The company also issued approximately 228 million shares from its previously announced entitlement offer, which it said would raise approximately $3 million before costs and leave it funded through to the production milestone.