Alpha HPA Says Stage 2 Is More Than 55% Complete, Targets Late 2027 Start

A4N: $0.410 +17.14% · MC: $559M

Alpha HPA’s Stage 2 project is reported more than 55% complete, with commissioning targeted for around the fourth quarter of 2027 and production expected to commence in late 2027. The presentation cites over 13,800 tonnes covered by customer letters of intent, equivalent to more than 1.3 times planned production, and forecasts annual steady-state EBITDA of approximately $289 million; these are project targets and forecasts, not achieved results. The update follows Alpha HPA’s recent commencement of the process to draw down its $160 million Export Finance Australia commitment, with disbursements subject to documentation and approvals.

Source announcements: 2026-11-05 09:36 to 2026-11-05 09:36 Sydney time
Story updated 2026-11-05 10:30 Sydney time