Maritana Advances Black Swan Hub Construction, Extends Early Works
MRT: $0.550 -1.79% · MC: $205M
Maritana Minerals says construction at its Black Swan Processing Hub is progressing, with demolition complete and concrete work underway on the new carbon-in-leach circuit; first gold remains targeted for the second half of 2027. The early works agreement with GR Engineering Services has been extended to the end of December at an additional committed cost of approximately $20 million, following an earlier commitment of approximately $32 million, while the main EPC contract is still being finalised.