Element 25 Nears Butcherbird Construction as Louisiana Project Is Reset

Element 25 has advanced Butcherbird towards construction, with early works materially complete, engineering substantially finished and main construction scheduled to begin in the fourth quarter of 2026, subject to closing financing of approximately $50 million. In parallel, its Louisiana project is being reshaped after GM supply and financing agreements ended; revised Stellantis arrangements remain subject to definitive documents, while the company assesses funding options under changed US grant terms.

Updated 06 Nov 2026, 07:59 AM Sydney time
Share
SourcesU.S.A. HPMSM Project UpdateInvestor Update - IMARC ConferenceButcherbird Expansion Enters Main Construction PhaseNotice of Annual General Meeting/Proxy FormApplication for quotation of securities - E25
Comments

Element 25 Resets Louisiana Project as GM Agreements End and Stellantis Deal Is Reworked

2026-10-30 · Materials

E25: $0.205 -4.65% · MC: $62M

Element 25 says revised terms for its approximately US$166 million US Department of Energy grant support a changed development plan for its planned Louisiana manganese-processing project, while it evaluates debt, strategic equity and project-level investment options. Its GM supply and financing agreements have been mutually terminated, and revised Stellantis offtake and prepayment arrangements are agreed in principle but still require definitive documents. The company also made an initial submission to a US critical-minerals consortium process, with no assurance of an award.

Updated 2026-10-30 09:52
Share
SourcesU.S.A. HPMSM Project Update
Comments

Element 25 Says Butcherbird Expansion Early Works Are Materially Complete

2026-10-29 · Materials

E25: $0.215 +2.38% · MC: $62M

Element 25 says early works for its Butcherbird manganese expansion are materially complete, with site infrastructure established and major equipment packages awarded, ordered and in manufacture. Detailed engineering is materially complete, operational readiness work is advanced, and the company says financing close is approaching; the project is intended to lift concentrate production to over one million tonnes a year.

Updated 2026-10-29 11:44
Share
SourcesInvestor Update - IMARC Conference
Comments

Element 25 advances Butcherbird expansion towards main construction

2026-10-28 · Materials

E25: $0.210 +2.44% · MC: $62M

Early site works at Element 25’s Butcherbird expansion are materially complete, with construction-ready areas and supporting infrastructure prepared for the next phase. The company says detailed engineering is substantially complete, key commercial agreements have been signed and it has made significant progress towards closing a financing package of approximately $50 million; main construction is scheduled to begin in the fourth quarter of 2026. Separately, Element 25 issued ordinary shares after performance rights were converted, and its annual meeting is scheduled for November.