Element 25 advances Butcherbird expansion towards main construction
E25: $0.210 +2.44% · MC: $62M
Early site works at Element 25’s Butcherbird expansion are materially complete, with construction-ready areas and supporting infrastructure prepared for the next phase. The company says detailed engineering is substantially complete, key commercial agreements have been signed and it has made significant progress towards closing a financing package of approximately $50 million; main construction is scheduled to begin in the fourth quarter of 2026. Separately, Element 25 issued ordinary shares after performance rights were converted, and its annual meeting is scheduled for November.